编者按:精品学习网项目管理师考试频道为参加2012年项目管理考试的考生朋友搜集整理2012年项目管理认证练习题(中英文),供大家参考复习!在此祝愿大家考试成功!
1. In fixed price contract which of the following holds true?
The seller agrees to use his best effort to fulfill the contract within the estimated contract amount.
The seller agrees to perform a service or furnish supplies at the established contract price.
If the amount of the contract is exceeded the seller is not obligated to perform further unless the buyer increases the funds.
More risk is placed on the buyer.
在固定价格合同中以下哪一条是正确的?
卖方同意在估算合同总量内尽最大努力履行合同
卖方同意在确定的合同价格上提供服务或供应
除非买方提高金额,若超出合同额卖方不负责履行超出部分
买方承担较大风险
2.If the project was supposed to have $1.000worth of work accomplished, but only completed $850 worth of work, what is the Scheduled Variance?
$150
$1.500
Cannot calculate from the information provided
.-$150
若项目完成预计价值$1.000,但仅完成$850的工作, 则进度偏差为:
$150
$1.500
以上资料无法计算
-$150
3.Using the table below, what is the Present Value of an annual expenditure of $4,000per year over the next three years at 10% pre year?
Year |
Present Value of $1 at 10% |
Present Value of $1 at 12% |
1 |
0.909 |
0.893 |
2 |
0.826 |
0.797 |
3 |
0.751 |
0.712 |
4 |
0.683 |
0.636 |
-$9,608
-$7,206
_$9,944
$6,551
运用下表,计算年金流出流量为$4,000三年后的现值(利率10%/年).
年度 |
$1在10%的利率下现值 |
$1在12%的利率下现值 |
1 |
0.909 |
0.893 |
2 |
0.826 |
0.797 |
3 |
0.751 |
0.712 |
4 |
0.683 |
0.636 |
-$9,608
-$7,206
_$9,944
$6,551
4. The initial cost of your project is $25,000, which will save the company $6,000 per year for the next four years. Using the above table. If your company wants a 12% ROI, what is the NPV of the project?
-$1,000
_$6,772
+$1,758
+$6,772
你的项目的初始费用为$25,000,而在今后的四年中每年将为公司节省$6,000,运用上表,若你的公司想获得12%的投资回报(ROI),则该项目的NPV净现值是:
-$1,000
_$6,772
+$1,758
+$6,772
5. ABC company commonly used Sum of the Years method to calculate depreciation on assets. They purchased a computer which cost $15,000, knowing they can sell it at the end of three years for $3,000. How much depreciation is taken the third year?
$4,000
$2,000
$7,500
$2,500