ABC公司通常使用年数和计折旧法计算资产折旧. 他们购买了一台价值$15,000的计算机,在第三年末该机可以$3,000的价格出售,则第三年所提的折旧为:
$4,000
$2,000
$7,500
$2,500
6. Your company has established a reward and recognition system for its project management professionals. Project cost performance is used as a criterion to determine rewards. What should you do to ensure that rewards reflect actual performance?
Consider overtime work as part of the job
Prepare a cost baseline
Use earned value management to monitor performance
Estimate and budget controllable and monitor performance
你们公司为项目管理的专业人士建立了一套奖励与考评系统. 项目成本业绩即是决定奖励的标准之一. 为了确保所给出的奖励能真正反映实际的业绩,你应该采取什么措施?
将加班视为工作的一部分
设定一个成本基线
利用挣值管理来监控业绩
对可控和不可控成本分别做出评估和预算
7. On a small project, one of the vendors informs the PM that he will substitute a better quality pipe for the pipe included in the initial plan since the pipe originally quoted is unavailable. Due to circumstances, the vendor indicated there would be no additional cost to the project. He also informs the PM that, due to a slight delay in delivery of the pipe, he will work on another task ahead of schedule. Where will the PM record these modifications?
WBS
Cost change control
Scope change control
Project schedule
A & d
在一个小项目中,一个供应商通知项目经理他将用高质量的管道替代原有管道,此方案放到立项计划里,因为管道的原先的报价没有. 鉴于这种情况,供应商提出他们不增加项目成本. 他同时告诉项目经理因为管道有一点延迟,他将做其他超出进度的工作. 项目经理将把此变更记在那里?
工作分解结构
成本变更控制
范围变更控制
项目进度
A 和 d
8. To integrate approved scope changes, the PM should begin with:
Approved budget
Project schedule
Human resource requirements
Product description
WBS
为了综合的批准范围变更,项目经理首先应当开始:
批准预算
确定项目进度
寻找人员
产品描述
工作分解结构WBS