2012年项目管理认证练习题(中英文)5

2012-01-29 16:57:20 字体放大:  

编者按:精品学习网项目管理师考试频道为参加2012年项目管理考试的考生朋友搜集整理2012年项目管理认证练习题(中英文),供大家参考复习!在此祝愿大家考试成功!

1. The Program Evaluation and Review Technique (PERT) is a method of scheduling projects. In the context of risk, PERT is better than the Critical Path Method because it deals with the _______ associated with ________.

Logic, cost estimates

Logic, schedule estimates

Certainty, cost estimates

Uncertainty, schedule estimates

Certainty, schedule estimates

计划评审技术(PERT)是项目进度安排的一种方法. 在风险的上下关联上,PERT比关键路径方法好,因为它处理_______同_______的关系.

a. 逻辑,成本估计

逻辑,进度估计

确定性,成本估计

不确定性,进度估计

确定性,进度估计

2. The project manager establishes a risk models that will be used on the Boston project. The risk model shows the risk events and provides the probabilities of occurrence. What is missing from this risk design?

a. Nothing, the risk design is complete

b. The risk probabilities need to be summed to determine the total project risk

The risk events must be labeled as internal or external risk events

The risk events do not address the technology used by the Boston project

The impact of the risk on the project’s objectives has not been assessed and assigned

一个项目经理建立的风险模型将在波士顿项目中使用. 风险模型显示风险事件,提供风险事件发生的可能性. 那一个是风险设计中所缺少的?

a. 没有,风险设计已经完成

b. 风险的可能性需要被汇总以决定整个项目的风险

c. 风险事件必须被标识为内部和外部的风险事件

d. 风险事件没有申请用在波士顿项目

e. 风险对项目目标的影响没有被评估和假定

3. Performance of a contract can bring liabilities other than the stated and implied warranty and guarantee that have implications of risk, but are perhaps not as visible. Two of these liabilities are ________ and ________ infringements.

Trade secret, technology

Process secret, advanced technology

Patent, copyright

Trade name, trade secret

Design and fabrication

执行合同能带来债务,它同规定的和隐含的保证和担保相比可能会牵扯到风险,但看不见. 两种这样的债务________和________被侵害.

a. 商业秘密,技术

b. 过程的秘密,先进技术

c. 专利权,版权

d. 商品名称,商业秘密

e. 设计,制作

4. The term deflection has a number of meanings, but in terms of pure risk mitigation strategies, deflection is accomplished by:

Performing contingent plans

Contracting to a sub-contractor

Allowing the owner to perform the mitigation strategy since the contractor feels it was not called for in

the contract

Allowing the float in the schedule to take care of the risk

降低风险有很多含义,但是对于纯风险减轻策略而言,通过什么可以降低风险:

a. 执行可能发生的计划

b. 同分包商签约

c. 允许业主执行减轻策略因为承包商感到偏差不会在合同中

d. 在进度中允许浮动时间以关注风险

5. It is possible to transfer risk through the use of insurance. If the estimated probability of damage occurring to an asset is 2 percent, the insurance cost is $5,000, and the total worth of the asset is $300,000, is it worth insuring the asset?

There is no advantage since the cost of the insurance equals the cost of the possible loss of the asset

The insurance costs less than the expected value of the loss, so therefore it is best to purchase the

insurance

Not desirable since it costs more to purchase the insurance than the expected value of the loss

Cannot determine form information provided

通过使用保险可以转移风险. 如果估计的伤害发生的可能性是资产的2%,保费是$5,000,全部资产价值$300,000,此保险是否值得?

a. 没有优势因为保险费同可能发生的资产损失的成本一样

b. 保费低于期望的损失值,因此最好执行

c. 没有意义因为保费比期望的损失值高

d. 从提供的数据中无法判断