2012年项目管理认证练习题(中英文)6

2012-01-29 16:58:48 字体放大:  

编者按:精品学习网项目管理师考试频道为参加2012年项目管理考试的考生朋友搜集整理2012年项目管理认证练习题(中英文),供大家参考复习!在此祝愿大家考试成功!

1. While identifying the risks associated with a new project, the PM finds that the vendor feels there is a 15% chance that their employees will go on strike. Which would impact the delivery of a critical component of the project? Upper management indicates there is a 25% probability there will be a hiring freeze which will limit the new personnel which can be hired for the team. What is the probability that both risk issues will occur and impact the success of the project?

37.5%

40%

3.75%

Not enough information provided

当对一个新项目进行风险识别时,项目经理发现卖主感觉到他们的雇员方面冒风险的可能性是15%,此风险将影响到项目关键内容的交付. 上级管理层指出租金被冻结的可能性是25%,租金冻结将限制项目组成员的雇佣. 两个反向同时发生而影响项目成功的可能性是多少?

a. 37.5%

b. 40%

c. 3.75%

d. 没有提供足够的信息

2. In general, disagreements among stakeholders should be resolvedin

Sponsor

Customer

Performing organization

Senior management

None of the above

通常,利益相关者之间的分歧可通过——解决.

赞助者

顾客

执行机构

高级经理

以上均不是

3. When the project team is not collocated, establishing a way to help team members communicate quickly and frequently is essential. One practical approach is to---

Bring everyone together frequently for meetings

Conduct informal audioconference meetings regularly

Hold a project kickoff meeting

Set up an electronic yearbook that lists each team member’s accomplishments and background

All the above

当项目组尚未组建时,建立一条有助于团队成员及时迅速沟通的途径至关重要. 一条可行的途径是:

频繁召集所有人召开会议

有规律的举办非正式的听证会

举办项目启动会

制定电子年鉴列出成员的资历和背景

以上全部.

4. A project manager who wants to create a receptive atmosphere for communicating should

Ensure that all communication is clear and understood

Speak or write as he or she would like to be spoken or written to

Have the project team prepare a project communication plan

Ensure that team members have the information needed to do their work

Ensure that team members have the tools available to facilitate

一个期望营造易于接受的沟通气氛的项目经理应该

确保所有交流清晰易懂

以他或她自己喜欢的方式与别人交谈或纸上交流

让项目组准备一个项目沟通计划

确保项目组成员获得其任务所需的信息

确保项目组成员获得便利的工具.

5. The tool technique used for communication planning is—

Stakeholder analysis

Communication skills

Information retrieval systems

None of the above

用于沟通计划的工具技术是

利益相关者分析

沟通技巧

信息挽救系统

以上均不是