2012年项目管理认证练习题(中英文)20

2012-01-29 17:22:34 字体放大:  

6. If a company wants to measure up to the Malcolm Baldrige National Quality Award, which of the following criteria will they be evaluated to?

ISO 9000

Quality policy

Strategic planning

ANSI standards

如果一家公司想要达到获得Malcolm Baldrige国家质量奖, 下列哪一标准将会是他们要进行评估的?

ISO 9000

质量方针

战略规划

ANSI标准

7. When a process control chart is set up optimally, the upper and lower specification limits typically are:

Set equal to the upper and lower control limits

Set outside the upper and lower control limits

Set inside the upper and lower control limits

Set at two sigma from the mean value

当一个过程控制图表被很理想建立完成时, 其规格要求的上限和下限通常是:

设定等于控制范围的上限和下限

设在控制范围的上限和下限之外

设在控制范围的上限和下限之内

设在均值的二个西格玛sigma 水平

8. Which of the following quality gurus believe “zero-defects” is achievable?

Deming

Juran

Crosby

Taguchi

下列哪一质量大师相信 "零-缺陷" 是可达到的?

Deming

Juran

Crosby

Taguchi

9. A Linear Responsibility Chart could be used in which of the following situations?

To show where responsible activities intersect with linear programming

To show various project responsibilities

To show linear activities that impact scheduling

To properly demonstrate a linear curve relationship

线性责任图能用在下列哪种情形:

表示在什么地方责任活动与线性规划重合

表示各种项目责任

表示影响进度的线性活动

适当展现线性曲线关系

10. A major concern of the project sponsor during integration activities is:

The impact of the project on the organization’s ongoing operations

The amount of technical work to be accomplished in each department

The number of functional boundaries that are crossed

The preparation of scheduling and performance reports.

在项目整合活动期,项目业主重要关注的是:

项目对组织目前运作的影响

每个部门要完成的技术工作量

要涉及的职能部门的数量

进度和绩效报告的准备