2012年项目管理认证练习题(中英文)21

2012-01-29 17:29:08 字体放大:  

编者按:精品学习网项目管理师考试频道为参加2012年项目管理考试的考生朋友搜集整理2012年项目管理认证练习题(中英文),供大家参考复习!在此祝愿大家考试成功!

1. Which of the following techniques can be used to integrate and measure a project’s schedule and cost performance?

Earned value management

Monte Carlo Process

Quality Management Plan

Utilize a matrix structure

要整合和衡量项目进度和成本绩效,能用下列哪项技术方法:

挣值管理

蒙托卡罗方法

质量管理计划

利用矩阵结构

2. A fully integrated project plan assists the project manager by:

Providing a complete reference for all organizational policies.

Providing the project manager with total project authority

Preventing input from the project sponsor.

Facilitating communications among project stakeholders.

完全整合的项目计划对项目经理的帮助是通过:

对所有的组织政策提供完全的参考

给项目经理全面职权

保护项目业主的投入

方便项目相关者之间的沟通

3. The true status of a project cannot be determined unless which of the following are jointly considered:

Project schedule and cost analysis

Project schedule and employee responsibilities

Scope baseline and management plan

Cost analysis and deliverables

要知道项目真实状态,必须结合考虑下列哪一项:

项目进度和成本分析

项目进度和员工责任

范围基准和管理计划

成本分析和工作成果

4. Which of the following is not used for reporting performance?

Bar charts

S-curves

Histograms

Fishbone diagrams

下列哪一种技术没有被用来报告绩效:

柱线图

S曲线

矩形图

鱼刺图