1. Which of the following techniques can be used to integrate and measure a project’s schedule and cost performance?
Earned value management
Monte Carlo Process
Quality Management Plan
Utilize a matrix structure
要整合和衡量项目进度和成本绩效,能用下列哪项技术方法:
挣值管理
蒙托卡罗方法
质量管理计划
利用矩阵结构
2. A fully integrated project plan assists the project manager by:
Providing a complete reference for all organizational policies.
Providing the project manager with total project authority
Preventing input from the project sponsor.
Facilitating communications among project stakeholders.
完全整合的项目计划对项目经理的帮助是通过:
对所有的组织政策提供完全的参考
给项目经理全面职权
保护项目业主的投入
方便项目相关者之间的沟通
3. The true status of a project cannot be determined unless which of the following are jointly considered:
Project schedule and cost analysis
Project schedule and employee responsibilities
Scope baseline and management plan
Cost analysis and deliverables
要知道项目真实状态,必须结合考虑下列哪一项:
项目进度和成本分析
项目进度和员工责任
范围基准和管理计划
成本分析和工作成果
4. Which of the following is not used for reporting performance?
Bar charts
S-curves
Histograms
Fishbone diagrams
下列哪一种技术没有被用来报告绩效:
柱线图
S曲线
矩形图
鱼刺图