5. Communication technology factors that may affect the project include all but which one of the following?

A specific type of project instruction

The immediacy of the need for information

The availability of technology

The expected project staffing

可能影响项目的沟通技术因素包括所有下列事项,除了:

a. 专门类型的项目说明书

b. 信息需要的迫切性

c. 技术的可用性

d. 项目期望的人员配置

6. The project manager issued a series of status reports over the course of several months to address issues that had emerged in project negotiations with the contractor. This represents what form of communication?

Formal verbal communication

Formal written communication

Informal verbal communication

Informal written communication

项目经理发出了关于数月来项目状态一系列报告,用以表明在与合同方的项目谈判中出现的问题,这表示的是什么形式的沟通:

正式的言语沟通

正式的书面沟通

非正式的言语沟通

正式的书面沟通

7. Project management software:

Cannot be used as a communication tool

Is not considered a class of computer applications

Can assist with both planning and controlling project costs and schedules

Guarantees on time project completion

项目管理软件:

不能用作沟通工具

没有被考虑为高级的计算机应用

能用来帮助规划和控制项目成本和进度

保证项目按时完成

8. Debra realizes she must determine the aspects of her project that may be at risk. Which of following is not a useful tool for her to use in identifying these risks?

Ishikawa diagrams

System or process flowcharts

Interviews with stakeholders

Corrective action

Debra 认识到她必须决定项目可能在哪些方面有风险. 在识别这些风险中,下列哪一工具对她没有什么用处?

Ishikawa 图

系统或方式流程表

与项目相关者面谈

纠正行动