1. A door panel for a new car is inspected prior to installation on the automobile. This is an example of:

Prevention

Variable Sampling

Quality Assurance

Quality Control

新汽车的仪表盘在安装前已经被检验. 这是下列那一种的例子:

预防

可变样本

质量保证

质量控制

2. A thunderstorm caused intermittent power outages during a 24-hour period. When the day’s production run was sampled it was found that over 50% of the products produced were defective. These defects are an example of :

Variable sampling

Special causes

Prevention

Inspection

Random causes

一场雷暴造成24小时的停电. 白天生产的产品被发现有50%的不合格. 此种不合格是下列那一个的例子:

可变样本

特殊原因

预防性

检查

随即原因

3. A:PM wanted to show management ,visually, how quality controls were affecting processes. the best tool to accomplish this is :

diagrams

Histograms

Flowcharts

Control charts

Statistical samples

项目经理想向管理层显示可视的质量控制对过程的影响. 完成它最好的工具是:

Pareto 图

柱状图

流程图

控制图

统计样本

4. A PM is developing the projects budget and wants to have adequate resources to implement a solid quality control program. His project will cost approximately $110.00.What is the minimum amount he should include in the project budget for the quality program?

$10,000

$7,500

$6,135

$3,300

$5,500

一个项目经理正项目预算同时想使用适当的资源完成稳固的质量控制程序. 它的项目成本大约是$110.00,他应当在项目预算中对质量的预算最少做多少?

$10,000

$7,500

$6,135

$3,300

$5,500

5. Repeating the initiating processes at the beginning of each phase to keep the project focused on:

Interaction between phases.

The details of the project using rolling wave planning

Process group overlapping within each phase.

Business needs.

在每一阶段初期重复立项过程以保证项目着重于:

阶段间的交互

项目运用滚动波浪计划的细节

在每一阶段工艺组有重叠

商业需要