6. In the integration management process, the project development uses the outputs of the other planning processes to create a consistent, coherent document that can be used to guide both project______
Execution, control
Control, termination
Scope management, integration
Initiation and close-out.
在综合管理程序中,项目开展使用其他计划过程的输出以形成一个持续的,连贯的文件以便用于同时指导项目的___.
实施,控制
控制, 终止
范围管理,综合
立项,收尾
7. Of the PMBOKTM’s five project management process groups, which group is a common thread that spans the majority of these processes from the start to finish?
Executing
Planning
Controlling
Initiating
Closing
PMBOKTM’s的五个项目管理过程组中,哪一个过程组由始至终作为共同的线索跨越了绝大多数的过程?
实施
计划
控制
立项
收尾
8. Of the PMBOKTM’s five project management process groups, which group has the highest level of activity throughout the life of the project?
a. Executing
Planning
Controlling
d. Initiating
PMBOKTM’s的五个项目管理过程组中,哪一个过程组在项目整个寿命周期内拥有工序的最高级别?
a. 实施
b. 计划
c. 控制
d. 立项
9. The integrated project plan provides the baseline of:
The risk identification process
Any corrective action to be taken
Which changes will be controlled
Any work performance system.
综合项目计划提供了___基线?
风险辨别程序
任何实施的纠正措施
将被控制的变化
任何工作执行系统
10. Which of the following functions does NOT pertain to the roles and responsibilities of the project manager?
Planning
Staffing
Controlling
Directing
以下功能中哪一项不属于项目经理的角色和职责?
计划
人员招募
控制
指导